BIA/TOWNSHIP/REGION
Schedule Updates
Stage 1 progress this week:
- Interlocking paving continues
- Poured sidewalk beside Rutledge Jewellers on Church St.
Anticipated next week:
- Remove and replace damaged sidewalk outside of #71-77 Brock St.
- POSSIBLE filling of planter boxes and tree pits
Phase 2: Progress this week:
- Installation of sidewalks on both north and south sides
- Poured concrete base for interlocking
- Began laying interlocking brick on north side of street
- Street lights installed
- Road grading completed - asphalt ready
Anticipated next week:
- Interlocking continuing
- Grading on private property and driveway restoration
- Street lights installed in planters where applicable
- Asphalt road surface
For information or questions call Bev 852-0688 or Scott 852-7846
|